Invitation for Contract Awards Detail
GOVERNMENT OF THE PEOPLE'S REPUBLIC OF BANGLADESH
| Ministry/Division |
: |
Ministry of Housing and Public Works |
| Agency |
: |
Rajdhani Unnayan Kartripakkha (RAJUK) |
| Procuring Entity Name |
: |
Project Director, Urban Resilience Project: RAJUK Part |
| Procuring Entity Code |
: |
|
| Procuring Entity District |
: |
Dhaka |
| Contract Award for |
: |
Goods |
| Invitation/Proposal Reference No |
: |
ICB-1(G)/2020-21 |
KEY INFORMATION
|
| Procurement Method |
: |
ICT |
| Tendering Method |
: |
Open Tendering Method |
FUNDING INFORMATION
|
| Budget and Source of Funds |
: |
Development Budget Grant/Credit |
| Development Partner (if applicable) |
: |
IDA |
PARTICULAR INFORMATION
|
| Project/Programme Name (if applicable) |
: |
|
| Tender/Proposal Package No |
: |
URP/RAJUK/G-24 |
| Tender/Proposal Package Name |
: |
Procurement of Equipment: Cutter Crane with 10 inch RCC Slab Cutting Capacity & 3.65 Ton Lifting Capacity |
| Date of Advertisement |
: |
11/11/2020 |
| Date of Notification of Award |
: |
01/02/2021 |
| Date of Contract Signing |
: |
07/02/2021 |
| Proposed Date of Contract Completion |
: |
February 2022 |
| No. of Tenders/Proposals Sold |
: |
1 |
| No. of Tenders/Proposals Received |
: |
1 |
| No. of Tenders/Proposals Responsive |
: |
1 |
INFORMATION ON AWARD
|
| Brief Description of Contract |
: |
Supply of 1 Item: Cutter Crane (RCC Slab Cutting Capacity: 10 inch & Lifting Capacity: 3.65 Ton) (1 No.); Delivery, Installation & Setting up: 180 days from the date of Contract Sign; Local level detailed hand-on O&M Training: 12 months from the date of Contract Sign. |
| Contract Value |
: |
USD 350,000.00 (In Words: US Dollar Three hundred Fifty thousand only) |
| Name of Supplier/Contractor/Consultant |
: |
M/s. Sarker Kabir Ahamed |
| Location of Supplier/Contractor/Consultant |
: |
31 Bir Uttam K.M. Shafiullah Road, Dhaka-1205, Bangladesh |
| Location of Delivery/Works/Consultancy |
: |
Dhaka |
| Is the Contract Signed with the same person stated in the NOA |
: |
Yes |
| If No give reason why |
: |
|
| Was the Performance Security provided in due time? |
: |
Yes |
| If No give reason why |
: |
|
| Was the Contract Singed in due time? |
: |
Yes |
| If No give reason why |
: |
|
ENTITY DETAILS
|
| Name of Authorised Officer |
: |
Abdul Latif Helaly |
| Designation of Authorised Officer |
: |
Project Director |